Equinix DB5- Fibre backbone infrastructure, cabling and terminations & security and access control packages

TEAM SIZE

12 guys

CABLE PULLED

16km

SAFETY COMPLIANCE

0 lost-time incidents

PROJECT LENGTH

6 months

Scope of Work

Design and installation of the fibre backbone infrastructure, cable management, and containment package at Equinix DB5, Dublin. This included fibre containment, routing systems, and LV containment across multiple data halls.

Challenges & Solutions

Project coordination between multiple trades in a live construction environment. DTEE implemented modular containment assemblies to accelerate fit-out and reduce on-site fabrication. Collaboration with GBE Electronics ensured seamless fibre pathway alignment and reduced rework.

Outcomes

Delivered on time and in full compliance with Equinix and GBE standards. DTEE’s containment quality was rated ‘excellent’ in the client completion audit.

Compliance

ISO 9001, ISO 45001, I.S. 10101 / BS 7671 compliance, Safe Electric certification.