Equinix AMS 17- LV cable pulling and temination package

TEAM SIZE

10 electricians and Gos

CABLE PULLED

7km

SAFETY COMPLIANCE

0 lost-time incidents

PROJECT LENGTH

8 weeks

Scope of Work

LV cabling, containment installation, and termination works across approximately 7 km of cable in a live data centre environment. Delivered over 8 weeks by a 10-person DTEE team.

Challenges & Solutions

Work carried out in a live operational data centre. DTEE applied strict isolation, lock-out/tag-out procedures, and progressive QA verification. Daily interface meetings with client teams ensured safe and efficient progress.

Outcomes

Delivered with zero incidents, 100% QA pass rate, and no disruption to existing operations. Commended by client H&S team for exemplary compliance.

Compliance

I.S. 10101 / BS 7671, ISO 9001, ISO 45001, Safe Electric Registered Contractor.