Equinix AMS 10- LV cable pulling and temination package

TEAM SIZE

12 electricians and Gos

CABLE PULLED

12km

SAFETY COMPLIANCE

0 lost-time incidents

PROJECT LENGTH

6 weeks

Scope of Work

LV cabling, containment installation, and terminations for Equinix AMS10 data centre in Amsterdam. Delivered by a team of 12 electricians and general operatives within a 6-week programme.

Challenges & Solutions

Project executed during Covid-19 lockdown with access restrictions. DTEE implemented Safe-Work Protocols, staggered shifts, isolation zones, and digital toolbox talks. Field reporting tools ensured live progress tracking and client transparency.

Outcomes

Delivered on time and within budget, with 0 lost-time incidents, 100% QA compliance, and seamless integration with local mechanical and commissioning teams.

Compliance

I.S. 10101 / BS 7671, ISO 45001, ISO 9001, Covid-Safe Operational Procedures.